Overall Network Design
Phase II Tentative Schedule

National LambdaRail Update
Overall Network Design

National LambdaRail Update
Phase I Layer 1 Deployment – Completed Sept ‘04

National LambdaRail Update
Phase II Layer I Deployment

National LambdaRail Update

National LambdaRail Update
Layer 2 Network Design

National LambdaRail Update
Layer 3 Network Design

National LambdaRail Update
Phase I PoP Layout

National LambdaRail Update
Phase II PoP Layout

National LambdaRail Update
Phase I & II Junction PoP Layout

National LambdaRail Update
Phase II Hut Layout

National LambdaRail Update
Phase II Tentative Schedule

National LambdaRail Update
Houston-El Paso
# Sites:  21
Projected Completion Date:  7/6/2005
KC-Houston
# Sites:  22 (20)
Projected Completion Date:  6/27/2005
El Paso-LA
# Sites:  24 (23)
Projected Completion Date:  8/16/2005
Houston-Baton Rouge
# Sites:  9 (8)
Projected Completion Date:  7/13/2005

National LambdaRail Update
El Paso-Denver
# Sites:  14
Projected Completion Date:  8/30/2005
DC-NYC
# Sites:  9
Projected Completion Date:  7/22/2005
NYC-Cleveland
# Sites:  25 (19)
Projected Completion Date:  8/3/2005
Jacksonville-Baton Rouge
# Sites:  15
Projected Completion Date:  9/14/2005

National LambdaRail Update
Ogden-SLC
# Sites:  2
Projected Completion Date:  8/18/2005

For more information…
NLR puts the control, the power and the promise of experimental
Contact Tom West twest@nlr.net
NLR: putting the control, the power and the promise of experimental network infrastructure in the hands of our nation’s scientists and researchers.